Projects

Tanesco Tanzania

Verkís services is review of tenders and contracting, design review, mechanical and electrical shop inspections, project management, site supervision and monitoring of refurbishing work, commissioning and guarantee inspection.

Tanesco has developed an emergency repair program for five hydro power plants in Tanzania and Verkís together with Landsvirkjun Power has been contracted as the owner’s engineer for this project. The project has been supported by the Norwegian Water Resources and Energy Directorate (NVE).
Kidatu, 4×50 MW
Refurbishment of cooling and draining system
Replacement of governor system
Upgrade of the control system
Replacement of 11 kV switchgear
Kihansi, 3×60 MW
Replacement of chiller plant
Refurbishment of two governors
Mtera, 2×40 MW
Full inspection of units
Retrofit of 11 kV circuit breakers
Revitalization of diesel control automation
New Pangani, 2×34 MW
Reparation of Main Inlet Valve
Replacement of excitation system
Nyumba Ya Mungu, 2×4 MW
Inspection of Main Inlet Valve
Renew dewatering and drainage system
Replacement of batteries
Renew 11 kV generator circuit breaker

Technical information

Location:

Tanesco, Tanzania

Size:

4 – 60 megawatts

Project period:

2013 – 

 